How many days in advance must a person notify adjoining building owners of an upcoming excavation?

  1. 5 days

  2. 7 days

  3. 10 days

  4. 15 days

The correct answer is: 10 days

The correct answer is 10 days. This notification period is typically established to ensure that adjoining property owners are made aware of any impending excavation activities that could potentially impact their properties. Providing a 10-day advance notice allows adjoining owners adequate time to understand the scope of the excavation, assess any potential impacts on their own properties, and take any necessary precautions or steps to mitigate disruption. This practice not only promotes good neighborly relations but also helps to comply with local regulations designed to minimize disputes between property owners adjacent to excavation sites. Additionally, it aligns with standard practices in the construction and building inspection industry regarding communication and safety protocols. The other options represent shorter notification periods, which may not provide sufficient time for property owners to respond or prepare for the upcoming work.